Several tasks had to be completed before the insulation could happen. They were:
Electrical rough-in (subcontractor) HVAC rough-in (subcontractor) Plumbing top-out (Oz) Security system wiring (Oz and the boys) CAT-6 Internet cable wiring (Oz and the boys) Blocking for installation of brackets/handrails, etc. (Oz) Final installation of woodburning stove and chimney (Oz)
During the past month, all these things have been accomplished. So… we got started on placing insulation on the wall sections. We used R-19 batting for the exterior walls and R-13 for the interior insulation for the pantry. We insulated between the living area and the bedrooms (R-19), […]